Consultant Identification on Critical Risk Factors Affecting Construction Project Execution in Ghana
DOI:
https://doi.org/10.14738/assrj.410.3246Abstract
The consultants are front liners in execution of construction project and their perceived critical risk factors affecting construction project delivery is wealth considered and being aware to such hindrance will ensure efficient and effective project management technique to manage such risk should it occur. The purpose of the study was to identify critical risk factors affecting construction project delivery in Ghana. The study objective was to identify consultant’s perception on critical risk factors hindering construction execution and how to manage the risk. The study adopted a quantitative approach involving a cross-sectional design using survey, questionnaires administered to a population of 355 consultants of the Ghana Consulting Engineering Association (GCEA). Descriptive statistics, cross tabulations, factor analysis were used to analyse the resulting data. The study found that the most critical risk factors hindering construction delivery included high performance expectations, tight project schedule, poor program planning, excessive approval procedures, and bureaucracy of government. The study has establish that For all government funded projects, the main financial risk was the delay in payment and bankruptcy of stakeholders and main source of time overrun risks was enlargement of the project scope. The study further shown that the management of time schedule risk and financial risk included setting and agreeing on reasonable time lines , prompt payments on the part of stakeholders and obtaining reliable source of project funding, government to reduce the interest rates in order for stakeholders in construction projects to secure loans to fund projects respectively.
References
Adams, F. K. (2008). Construction contract risk management: A study of practices in the United Kingdom. Cost Engineering, 50(1), 22-33.
Agyakwa-Baah, A. (2009). A study into risk assessment and management practices within Ghanaian medium and large construction organizations. Unpublished MSc Project Management Dissertation, Built Environment Department, Sheffield Hallam University, United Kingdom.
Adu Gyamfi, T. and Boadaa, R. (2015). The effect of procurement management practices on risk management in construction firms. International journal of science: Basic Applied Research, vol.24 (3), 403 – 420.
Akintoye, A. S., & Macleod, M. J. (1997).Risk analysis and management in construction.International Journal of Project Management, 12(1), 31-38.
Al-Bahar, J., & Crandall, K. (1990).Systematic risk management approach for construction projects.ASCE Journal of Construction Engineering and Management, 116(3), 533-545.
Assibey-Mensah, G. O. (2008). Ghana’s construction industry and global competition: A research note. Journal of Black Studies, 39, 974-89.
Babbie, E. (2005). The basics of social research. Belmont: Thomson Wadsworth.
Bernstein, B. (1999) Vertical and horizontal discourse: an easy. British journal of sociology of Education, 6(2) 20-30.
Buertey, J. I. T., Abeere-Inga, F., &Kumi, T. A. (2012). Practical application of risk management techniques in infrastructural delivery: A case study of Ghanaian construction industry. Journal of Construction Project Management and Innovation, 2(1), 224 – 244.
Carter, R. L., & Doherty, N.A. (1974).Handbook of risk management. London: Kluwer-Harrap Handbooks.
Chapman, C., & Ward, S. (1997). Project risk management: Process techniques and insights. England: John Wiley and Sons Ltd.
Chapman, R. J. (2001). The controlling influences on effective risk identification and assessment for construction design management. International Journal of Project Management, 19(3), 147-160.
Chileshe, N., &Yirenkyi-Fianko, A. B. (2011). Perceptions of threat risk frequency and impact on construction projects in Ghana: Opinion survey. Journal of Construction in Developing Countries, 16(2), 115–149.
Chileshe, N. (2004). The application of TQM within small and medium sized construction related organizations. Unpublished PhD Thesis, School of Construction, Sheffield Hallam University, Sheffield, UK.
Claycamp, H. G. (2012). Probability concepts in quality risk management. Journal of Pharmacy, Science and Technology, 66(1), 78-89. doi: 10.5731/pdajpst.2012.00801.
Creswell, J. W. (2003) Research design qualitative, quantitative and mixed method approaches second edition. Sege publication califonia.
Dadzie, J., Abdul-Aziz, A. R., Kwame, A. (2012). Performance of consultants on government projects in Ghana: Client and contractor perspective. Journal of Business, 2(6), 256-267
Ehsan, N., Alam, M., Mirza, E., &Ishaque, A. (2010).Risk management in construction industry.Journal of Production and Performance Management, 61(2), 173-193
Ehsan A., Anjelo, F. D., Kujur, F. E., &Chaudhary, M. (2014). Risk management strategies for accidental risk occurrence on construction sites: A case study of Allahabad. Journal of Academia and Industrial Research, 3(2), 89-91.
Flanagan, R., & Norman, G. (1993).Risk management and construction. London: Blackwell Science Ltd.
Frimpong, Y., Oluwoye, J., & Crawford, L. (2003). Causes of delay and cost overruns in construction of groundwater projects in developing countries: Ghana as a case study. International Journal of Project Management, 21, 321-26.
Ghahramanzadeh, M. (2013). Managing risk of construction project a case study of Iran. Retrieved on October 20, 2014 from http://www.riskmanagementinsight.com/media/docs/FAIR_introduction.pdf
Godfrey, P. (1996). Control of risk: A guide to the systematic management of risk from construction. London: Construction Industry Research and Information Association.
Hassanein A. G., &Afify, H. M. (2007). Contractor’s perceptions of construction risks: A case study of power station projects in Egypt. Cost Engineering, 49(5), 25-34.
Hayes, R., Perry, J., & Thompson, J. (1986).Risk management in engineering construction: a guide to project risk analysis and risk management. London: Thomas Telford.
Hillson, D., & Murray-Webster, R. (2004).Understanding and managing risk attitude. Accessed on September 16, 2014 from http://www.kent.ac.uk/scarr/events/finalpapers/Hillson%20%2B%20Murray-Webster.pdf
Hopkin, P. (2012). Fundamentals of risk management (2nd ed.). London: Kogan-Page.
Hubbard, H. (2009). The failure of risk management: Why it's broken and how to fix it.Chichester: John Wiley & Sons.
Ijaola, I. (2012). An analysis of contractors’ approaches to risk management practices in Lagos state, Nigeria. In S.
Laryea, S.A. Agyepong, R. Leiringer, and W. Hughes, (Eds), Proceedings of the 4th West Africa Built Environment Research (WABER) Conference,24-26 July 2012, Abuja, Nigeria, pp. 687-695.
Jean-Lou, C. M., Dorne, G. E. N., Kass, L. R., Bordajandi, B. A., Ulla B., Castoldi, A. F., Heppner, C., Eskola, M., Fabiansson, S., Ferrari, P., Scaravelli, E., Dogliotti E., Fuerst, P., Boobis, A. R., & Verger, P. (2011). Human risk assessment of heavy metals: principles and applications. In S. Astrid, S. H, S.
Jones, J. A. (2006). An introduction to factor analysis of information risk (FAIR).Retrieved on October 14, 2014 from http://www.riskmanagementinsight.com/media/docs/FAIR_introduction.pdf
Key, J. P. (1997). Qualitative research. Retrieved July 24, 2007, from http://www.okstate.edu/ag/agedcm4h/academic/aged5980a/5980/newpage21.htm
Kishk, M., &Ukaga, C. (2008).The impact of effective risk management on project success. Proceedings of the 24th Annual ARCOM Conference, 1-3 September 2008, Cardiff, UK, Association of Researchers in Construction Management, (pp.799-808).
Krejcie, R. V. and Morgan, D. W. (1970) Determining the sample size for research activities. Journal of Educational and psychological measurement, (30) 607- 610.
Laryea, S. (2011).Risk accountability in the tender process of contractors in Ghana and UK. International Journal of Project Organisation and Management, 3 (3-4), 290-306.
Mumtaz, M. M., Hugh, H., & Hana, P, R. (2011). Mixtures and their risk assessment in toxicology. In S. Astrid, S. H, S.
K. O. Roland. (Eds.), Metal ions in toxicology. RSC Publishing (pp.61–80). R. Müller, "Leadership Competences in Projects," in Advanced Project Management, T. Mayer, R. Gleich, A. Wald and R. Wagner, Eds., Münster, Lit-Verla, 2010
Noor, I., &Tichacek, R. (2009). Contingency Misuse and other risk management pitfalls. Cost Engineering, 51(5), 28-33.
Odonkor, A. K. (2011).The effect of strategic risk management on project delivery: A case study of the construction industry in Ghana.Unpublished thesis for Commonwealth Executive Master of Business Administration Institute of Distance Learning, KNUST
Oladinrin, O., Olatunji, A., &Hamza, B. (2013).Effect of selected procurement systems on building project performance in Nigeria.International Journal of Sustainable Construction Engineering and Technology, 4(1), 12-23.
Panthi, K., Ahmed, S., Ogunlana, S. (2009). Contingency estimating for construction projects through risk analysis. International journal of construction education and research, 5, 79-94.
Perera, B., Dhanasinghe, I., &Rameezdeen, R. (2009). Risk management in road construction: the case of Sri Lanka. International Journal of StrategicProperty Management, 13, 87-102.
Popova-Clark, J. (2011). Risk management: Better, but still not there yet. Retrieved on February 15, 2014 from http://www.dataanalytics.com/pdf/BetterRiskMgt.pdf
Pourrostam, T., & Ismail, A. (2011).Significant factors causing and effects of delay in Iranian construction projects.Australian Journal of Basic and Applied Sciences, 5(7), 450-456.
Project Management Institute (PMI). (2004). Project management body of knowledge (3rd ed.). New York: Project Management Institute, Inc.
Proske, D. (2008). Catalogue of risks: Natural, technical, social and health risks. Mount St. Helens, Washington: Springer
Razaque, A., Bach, C., Salama, N., &Alotaibi, A. (2012).Fostering project scheduling and controlling risk management.International Journal of Business and Social Science, 3(14), 12-26. nd
Sarantakos, S. (1998). Social research 2 edition. Basingstoke, Macmillan.
Sarantakos, S. (2005). Social research. Hampshire: Palgrave Macmillan.
Smallman, C. (1999). Risk and organizational behavior: A research model. Disaster Prevention and Management, 5(2), 12-26.
Smith, G., & Bohn, C. (1999).Small to medium contractor contingency and assumption of risk.Construction Engineering and Management, 125(2), 101-108.
Smith, A, Mortledge, R., & Kashiwagi, D. T. (2006). Building procurement. Oxford, U.K: Wiley Blackwell
Smith, N. J. (2003). Appraisal, risk and uncertainty. London: Thomas Telford Ltd. nd
Sohizadeh, R., Hassanzadeh, M., Raddum, H., & Hole, K. J. (2011).Quantitative risk assessment. Bergen: University Of Bergen. Retrieved on February 15, 2013 from http://www.nisnet.no/filer/Finse11/Risk%20Assessment.pdf
Wang, S. Dulaimi, M., &Aguria, M. (2004). Risk management framework for construction projects in developing countries. Construction Management and Economics, 22, 237-252
Ward, S., & Chapman, C. (2003). Transforming project risk management into project uncertainty management. International Journal of Project Management, 21(2), 97-105
Wiguna, I .P. A., & Scott, S. (2006).Relating risk to project performance in Indonesian building contracts.Construction Management and Economics, 24(11), 1125-1135.
Zou1, P. X. W., Zhang, G., & Wang, J-Y. (2006). Identifying key risks in construction projects: Life cycle and stakeholder perspectives. Retrieved on February 15, 2013from http://www.prres.net/papers/Zou_risks_in_construction_projects.pdf
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2017 Advances in Social Sciences Research Journal

This work is licensed under a Creative Commons Attribution 4.0 International License.