Risk Allocation and Sharing in Mega Industrial Projects from the Perspective of the New Yellow Book -FIDIC-2017 to Approach a Balanced Construction Contract
DOI:
https://doi.org/10.14738/tecs.121.16260Keywords:
Mega Industrial Projects, Risk allocation, Relative Importance Index, Frequency-Adjusted Frequency Index, Risk identification, optimal risk, risk management, FIDIC-2017 Yellow Book, Delay DamagesAbstract
Owners frequently allocate excessive risks to contractors and utilize (custom) contracts to fit their project needs and specifications. The MENA region has seen a boom in industrial projects in recent years, which has made it imperative to examine the barriers to optimal risk allocation and throw light on the processes currently in place for risk allocation. In order to approach a balanced construction contract, the current article aims to investigate the existing risk distribution in mega industrial projects. Properly identifying, evaluating, and assigning risks in contracts can improve project performance. First, the study found 70 risk factors that were categorized into nine groups based on a thorough literature review and scientometric analysis. Estimates of the likelihood, impact, and method of control for these risk factors were requested from the respondents. The findings showed that the way risk is now allocated in construction projects is ineffective and has resulted in a number of other issues, including aggressive contractual relationships, claims, and conflicts. Strong organizations today work hard to maintain effective partnerships by enforcing policies that promote cooperation and aid in risk management. Contractual provisions used in mega industrial projects become less flexible and less able to accommodate the needs and interests of the parties involved in all potential situations as a result of standardization. One of the most prominent standard forms of contracts for mega industrial projects, the Conditions of Contract for Plant and Design Build (FIDIC form 2017 Yellow Book), was researched and reviewed to identify risky provisions and offer solutions for contractual issues. In order to reduce the project's major risk factors and partially reform the contract requirements into risk-balanced conditions that may improve the contract's utility as a project management tool, several modifications were made. These amendments concentrated on the particular needs of mega industrial projects and made a concerted effort to address a number of issues, including the Employer and Contractor's responsibility matrix, liability limitations, resolving procurement-related issues, design errors and contradictions in documents, the necessity of coordination between contractors and subcontractors, the significance of following the project schedule, and the relationship between delay damages and project milestones. Contract parties will benefit from the study's findings in terms of effective project management, risk reallocation, management, and reduction of claims, as well as preventing disputes.
References
Abdullah, M.S., Alaloul, W.S., Liew, M.S. and Mohammed, B.S., 2018. Delays and cost overruns cause during construction of palm oil refinery projects. In MATEC Web of Conferences (Vol. 203, p. 02004). EDP Sciences.
Adam, A., Josephson, P.E. and Lindahl, G., 2015. Implications of cost overruns and time delays on major public construction projects. In Proceedings of the 19th International Symposium on Advancement of Construction Management and Real Estate (pp. 747-758). Springer, Berlin, Heidelberg.
ARCADIS, 2017, 2019, Construction disputes in the Middle East being resolved quicker than before.
Assaad, R., A. Elsayegh, G. Ali, M. Abdul Nabi, and I. H. El-adaway. 2020b. “Back-to-back relationship under standard subcontract agreements: Comparative study.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 12 (3): 04520020. https://doi.org/10.1061/(ASCE)LA.1943-4170 .0000406.
Assaad, R., and I. H. El-adaway. 2020c. “Enhancing the knowledge of construction business failure: A social network analysis approach.” J. Constr.
Eng. Manage. 146 (6): 04020052. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001831.
Bidua, A.K., 2018, November. Use of FIDIC 2017 as Standard Form of Contract for EPC Projects in Oil and Gas Industry. In Abu Dhabi International Petroleum Exhibition & Conference. Society of Petroleum Engineers.
Boateng, P., Chen, Z. and Ogunlana, S.O., 2015. An Analytical Network Process model for risks prioritization in megaprojects. International Journal of Project Management, 33(8), pp.1795-1811.
Chang, C.Y., 2014. Principal-agent model of risk allocation in construction contracts and its critique. Journal of Construction Engineering and Management, 140(1), p.04013032.
Cummins, T., 2015. Strategic contracting as a source of organizational success. Journal of Strategic Contracting and Negotiation, 1(1), pp.7-14. Dastyar, B., Esfahani, A.F., Askarifard, M. and Abbasi, A.M., 2018. Identification, Yellow Book -FIDIC-2017 to Approach a Balanced Construction Contract. Transactions on Engineering and Computing Sciences, 12(1). 54-102. Prioritization and Management of Construction Project Claims. Journal of Engineering, Project & Production Management, 8(2).
Eskander, R.F.A., 2018. Risk assessment influencing factors for Arabian construction projects using analytic hierarchy process. Alexandria engineering journal, 57(4), pp.4207-4218.
Gamal El-Din Nassar. Claims, Disputes and Arbitration. According to FIDIC Conditions of Contract for Civil, Mechanical, Electrical, Construction, Design/Build & Turkey, EPC & Short Form. Published by FIDIC (From 1953 up to 1999)
Gandhi, M. and Dey, A., 2017. Avoiding an arbitration dispute. International Journal of Innovative Research in Advanced Engineering, (09). Haapio, H. and Siedel, G.J., 2017. A short guide to contract risk. Routledge.
Haidar, A., 2011. Global claims in construction. Springer Science & Business Media.
Hiyassat, M.A., Alkasagi, F., El-Mashaleh, M. and Sweis, G.J., 2020. Risk allocation in public construction projects: the case of Jordan. International Journal of Construction Management, pp.1-11.
Hosseinian, S.M. and Carmichael, D.G., 2013. Optimal incentive contract with risk-neutral contractor. Journal of Construction Engineering and Management, 139(8), pp.899-909.
Hui, S. and Bai-zhou, H., 2013, November. Revision of the construction project contract model text in China. In 2013 6th International Conference on Information Management, Innovation Management and Industrial Engineering (Vol. 2, pp. 595-599). IEEE.
IACCM 2014 International Association for Contract and Commercial Management. Commercial Excellence: Ten Pitfalls to Avoid in Contracting. www.iaccm.comIACCM 2014 International Association for Contract and Commercial Management. Commercial Excellence: Ten Pitfalls to Avoid in Contracting. www.iaccm.com Illankoon, I.M.C.S., Tam, V.W., Le, K.N. and Ranadewa, K.A.T.O., 2019. Causes of disputes, factors affecting dispute resolution and effective alternative dispute resolution for Sri Lankan construction industry. International Journal of Construction Management, pp.1-11.
John E Miller, 2014. Managing contractual risk issues in commercial contracts. Contract Management, January 2014, pp.26-39 Keane, P.J. and Caletka, A.F., 2015. Delay analysis in construction contracts. Wiley Blackwell.
Khalef, R., El-adaway, I.H., Assaad, R. and Kieta, N., 2021. Contract risk management: A comparative study of risk allocation in exculpatory clauses and their legal treatment. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 13(1), p.04520036.
Khazaeni, G., Khanzadi, M. and Afshar, A., 2012. Fuzzy adaptive decision-making model for selection balanced risk allocation. International Journal of Project Management, 30(4), pp.511-522.
Komurlu, R. and Arditi, D., 2017. The role of general conditions relative to claims and disputes in building construction contracts. New Arch- International Journal of Contemporary Architecture, 4(2), pp.27-36.
Kumar, R.K. and Jegan, G.S., 2019. Risk Management of Contracts in Construction Projects. Risk Management, 6(04).
Li, Y., Wang, X. and Wang, Y., 2017. Using bargaining game theory for risk allocation of public-private partnership projects: Insights from different alternating offer sequences of participants. Journal of Construction Engineering and Management, 143(3), p.04016102.
Lim, B.T. and Loosemore, M., 2017. The effect of inter-organizational justice perceptions on organizational citizenship behaviors in construction projects. International Journal of Project Management, 35(2), pp.95-106.
Lu, W., Zhang, L. and Pan, J., 2015. Identification and analyses of hidden transaction costs in project dispute resolutions. International journal of project management, 33(3), pp.711-718.
Mahamid, I., 2013. Contributors to schedule delays in public construction projects in Saudi Arabia: owners' perspective. Journal of Construction Project Management and Innovation, 3(2), pp.608-619.
McCord, M., Davis, P. T., Haran, M., & Rodgers, W. J. (2015). Understanding delays in housing construction: Evidence from Northern Ireland. Journal of Financial Management of Property and Construction, 20(3), 286–319.
Melese, Y., Lumbreras, S., Ramos, A., Stikkelman, R. and Herder, P., 2017. Cooperation under uncertainty: Assessing the value of risk sharing and determining the optimal risk-sharing rule for agents with pre-existing business and diverging risk attitudes. International Journal of Project Management, 35(3), pp.530-540.
Mentis, M., 2015. Managing project risks and uncertainties. Forest ecosystems, 2(1), p.2.
Mohammadi, S. and Birgonul, M.T., 2016. Preventing claims in green construction projects through investigating the components of contractual and legal risks. Journal of cleaner production, 139, pp.1078-1084. Mona Abdel Hamid Hassanen, Ahmed Mohammed Abdelalim. Risk Identification and Assessment of Mega Industrial Projects in Egypt.
International Journal of Management and Commerce Innovation (IJMCI). Vol 10 Issue 1 April 2022-September
Nasirzadeh, F., Khanzadi, M., and Rezaie, M. (2014). “Dynamic modeling of the quantitative risk allocation in construction projects.” Int. J. Project Management. 32(3), 442–451.
Nasirzadeh, F., Mazandaran Zadeh, H. and Rouhparvar, M., 2016. Quantitative risk allocation in construction projects using cooperative-bargaining game theory. International Journal of Civil Engineering, 14(3), pp.161-170.
Nguyen, D.A., Garvin, M.J. and Gonzalez, E.E., 2018. Risk allocation in US public-private partnership highway project contracts. Journal of Construction Engineering and Management, 144(5), p.04018017.
Nguyen, P.T. and Nguyen, P.C., 2020. Risk Management in Engineering and Construction. Engineering, Technology & Applied Science Research, 10(1), pp.5237-5241.
Peckiene, A., Komarovska, A. and Ustinovicius, L., 2013. Overview of risk allocation between construction parties. Procedia Engineering, 57, pp.889-894.
Peter Fogh, Niklas Korsgaard Christensen, Anne-Sophie Truelsen, 2017. Major Changes in FIDIC Red, Yellow and Silver Book. PP.1-6 Pham, L.H. and Hadikusumo, H., 2014. Schedule delays in engineering, procurement, and construction petrochemical projects in Vietnam: A qualitative research study. International Journal of energy sector management.
Prasad, K.V., Vasugi, V., Venkatesan, R. and Bhat, N.S., 2019. Critical causes of time overrun in Indian construction projects and mitigation measures. International Journal of Construction Education and Research, 15(3), pp.216-238.
Yellow Book -FIDIC-2017 to Approach a Balanced Construction Contract. Transactions on Engineering and Computing Sciences, 12(1). 54-102.
Project Management Institute PMI. (2017). A Guide to The Project Management Body of Knowledge (PMBOK-Guide) - Sixth version, Pennsylvania, USA: Project Management Institute, Inc.
Project Management Institute, A guide to the project management Rameezdeen, R. and Rodrigo, A., 2014. Modifications to standard forms of contract: The impact on readability. Australasian Journal of Construction Economics and Building, The, 14(2), pp.31-40.
Saaidin, S., Endut, I.R., Samah, S.A.A. and Ridzuan, A.R.M., 2017. Stakeholder’s Perspective on Risks Allocation in Design and Build Projects in Malaysia. In MATEC Web of Conferences (Vol. 103, p. 03009). EDP Sciences.
Sadek, S. and Kulatunga, U., 2013. An overview of standard contractual forms modifications in the construction industry-the Middle East. Shafik, N., Qodsi, S., Serag, E. and Helmi, M., 2016. Application of FIDIC contracts under the Egyptian civil code. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 8(3), p.04516004.
Solimene, F., 2014. Use of FIDIC forms in the oil and gas construction sector and possible amendments to the Yellow and Silver Books. The Journal of World Energy Law & Business, 7(6), pp.558-571.
Subcommittee TI of the International Bar Association, 2013, Standard form of construction contracts Suprapto, M., Bakker, H.L., Mooi, H.G. and Hertogh, M.J., 2016. How do contract types and incentives matter to project performance? International Journal of Project Management, 34(6), pp.1071-1087.
Tang, Y., Chen, Y., Hua, Y. and Fu, Y., 2020. Impacts of risk allocation on conflict negotiation costs in construction projects: Does managerial control matter? International Journal of Project Management, 38(3), pp.188-199.
Tataretaghi, F. (2011). An Overview of Comparison between Parties of Construction Contracts in Malaysia. European Journal of Scientific Research, 49 (30): 415-420.
Tembo-Silungwe, C.K. and Khatleli, N., 2020. Development of risk misallocation causal networks using interpretive judgement in the construction industry. International Journal of Construction Management, pp.1-15.
Van Weele, A., 2014. International contracting: Contract management in complex construction projects. World Scientific.
Walsh, K.P., 2017. Identifying and mitigating the risks created by problematic clauses in construction contracts. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 9(3), p.03717001.
Wan, S., Ding, G., Runeson, G., Er, M. and Liu, Y., 2019, June. A Dynamic Model of Risk Allocation of Energy Efficiency Retrofits under Energy Performance Contract for Office Buildings in China. In Abstract Proceedings of 2019 International Conference on Resource Sustainability-Cities (acres Cities).
Wang, Y., Chen, Y., Wang, W. and Tang, Y., 2019. Differentiating two types of learning in contract design: Evidence from the construction industry.
Scandinavian Journal of Management, 35(1), pp.1-11. Youssef, A., Osman, H., Georgy, M. and Yehia, N., 2018. Semantic risk assessment for ad hoc and amended standard forms of construction contracts. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 10(2), p.04518002.
Zavadskas, E.K., Turskis, Z. and Tamošaitiene, J., 2010. Risk assessment of construction projects. Journal of civil engineering and management, 16(1), pp.33-46.
Zhang, L. and Qian, Q., 2017. How mediated power affects opportunism in owner–contractor relationships: The role of risk perceptions. International Journal of Project Management, 35(3), pp.516-529.
Abdelalim, A.M., 2019. “Risks Affecting the Delivery of Construction Projects in Egypt: Identifying, Assessing and Response”. In Project Management and BIM for Sustainable Modern Cities: Proceedings of the 2nd GeoMEast International Congress and Exhibition on Sustainable Civil Infrastructures, Egypt 2018–The Official International Congress of the Soil-Structure Interaction Group in Egypt (SSIGE) (pp. 125-154). Springer International Publishing.
Abd El-Karim, M.S.B.A., Mosa El Nawawy, O.A. and Abdelalim, A.M., 2017. Identification and assessment of risk factors affecting construction projects. HBRC journal, 13(2), pp.202-216.
Medhat, W., Abdelkhalek, H. and Abdelalim, A.M., 2023. “A Comparative Study of the International Construction Contract (FIDIC Red Book 1999) and the Domestic Contract in Egypt (the Administrative Law 182 for the year 2018)”, International Journal of Management and Commerce Innovations, Vol.11, Issue.1, pp.10-23.
Abd El-Hamid, M.S, Farag, S., Abdelalim, A.M., 2023, “Construction Contracts’ Pricing according to Contractual Provisions and Risk Allocation”, International Journal of Civil and Structural Engineering Research ISSN 2348-7607, Vol.11, Issue.1, pp.11-38.
Yousri, Elhosin, Ahmed El Badawy Sayed, Moataz A. M. Farag, and Ahmed Mohammed Abdelalim. 2023. "Risk Identification of Building Construction Projects in Egypt" Buildings 13, no. 4: 1084. https://doi.org/10.3390/buildings13041084.
Sherif Awad, Samir Gad, Abdelalim, A.M, 2023, “Critical Failure of Construction Projects and Their Remedial Actions from the Perspective of Applying Total Quality Management”, International Journal of Engineering, Management and Humanities (IJEMH), Vol.4, Issue.1, 147-167.
Khedr, R. and Abdelalim, A.M., 2021, “The Impact of Strategic Management on Projects Performance of Construction Firms in Egypt”, International Journal of Management and Commerce Innovations ISSN 2348-7585, Khedr, R. and Abdelalim, A.M., 2021, “Predictors for the Success and Survival of Construction Firms in Egypt”, International Journal of Management and Commerce Innovations ISSN 2348-7585 (Online), Vol. 9, Issue 2, pp.: (192-201).
Zou, X., & Vu, H. L. (2019). Mapping the knowledge domain of road safety studies: A scientometric analysis.
Accident Analysis and Prevention 132 (2019) 1052.
Cochran, W.G., 1977. Sampling techniques. John Wiley & Sons.
Naoum, S., Mustapha, F. H., "Factors influencing the effectiveness of construction site managers." International journal of project management 16, no. 1 (1998): 1-8. Mustapha, F. H., and S. Naoum. "Factors influencing the effectiveness of construction site managers." International journal of project management 16, no. 1 (1998): 1-8.
Odeh, A.M. and Battaineh, H.T., 2002. Causes of construction delay: traditional contracts. International journal of project management, 20(1), pp.67- 73
Al-Bahi, M.F., 1979. Statistical Psychology. Measuring the Human Mind, Cairo: Dar Al-Fikr Al-Arabi. Yellow Book -FIDIC-2017 to Approach a Balanced Construction Contract. Transactions on Engineering and Computing Sciences, 12(1). 54-102.
Abd El-Hamid, S., Abdelalim, A.M, 2021, “A Proposed System for Prequalification of Construction Companies & Subcontractors for Projects in Egypt”, International Journal of Management and Commerce Innovations ISSN 2348-7585, Vol. 9, Issue 2, pp.: 290-304.
Abdelalim, A.M., Elbeltagi, E. and Mekky, A.A., 2019. Factors affecting productivity and improvement in building construction sites, International Journal of Productivity and Quality Management, 27(4), pp.464-494.
Abdelalim, A.M., 2018, “IRVQM, Integrated Approach for Risk, Value and Quality Management in Construction Projects; Methodology and Practice”, the 2nd International Conference of Sustainable Construction and Project Management, Sustainable Infrastructure and Transportation for Future cities, ICSCPM-18, 16-18 December, 2018, Aswan, Egypt.
Amr Afifi, El. Samadony, A and Abdelalim, A.M., 2020, “Risk Response Planning for Top Risks Affecting Schedule and Cost of Mega Construction Projects in Egypt”, International Journal of Civil and Structural Engineering Research ISSN 2348-7607 (Online) Vol. 8, Issue 1, pp.: 79-93.
Amr Afifi, El. Samadony, A and Abdelalim, A.M., 2020, “A Proposed Methodology for Managing Risks in Construction Industry in EGYPT”, International Journal of Civil and Structural Engineering Research ISSN 2348-7607, Vol. 8, Issue 1, pp.: 63-78.
Abdelalim, A.M., El Nawawy, O.A. and Bassiony, M.S., 2016. ’Decision Supporting System for Risk Assessment in Construction Projects: AHP- Simulation Based. IPASJ International Journal of Computer Science (IIJCS), 4(5), pp.22-36.
Abdelalim, A.M., Mahmoud Eldesouky, 2021, “Evaluating Contracting Companies According to Quality Management System Requirements in Construction Projects”, International Journal of Engineering, Management and Humanities (IJEMH), Vol. 2, Issue 3, pp.: 158-169.
Abdelalim, A.M., Khalil, E.B. and Saif, A.A., 2021, “The Effect of Using the Value Engineering Approach in Enhancing the Role of Consulting Firms in the Construction Industry in Egypt”. International Journal of Advanced Research in Science, Engineering and Technology, ISSN: 2350- 0328 Vol. 8, Issue 2, pp. 16531-16539.
Ahmed Mohammed Abdelalim, Rizk Elimam A. Youni, Hesham Abdelkhalek, 2022, “Project Risk Management during Construction Stage According to International contract (FIDIC)”, Al-azhar University Research Magazine, Civil Engineering (CERM), Vol.10, Issue.2, pp.76-93.
Abd-Elhamed, A., Amin, H.E. and Abdelalim, A.M.,2020, “Integration of Design Optimality and Design Quality of RC buildings from the perspective of Value Engineering”, International Journal of Civil and Structural Engineering Research ISSN 2348-7607 (Online) Vol. 8, Issue 1, pp.:105-116
Zena A. Fadhel, El. Samadony and Abdelalim, A.M, 2020, “Studying the Applicability of Public Private Sector Partnership in the Reconstruction Projects in Iraq “International Journal of Civil and Structural Engineering Research ISSN 2348-7607, Vol. 8, Issue 1, pp.: 137-150.
Khaled Al-Barghouth, El. Samadony, A. And Abdelalim, A.M, 2016, “The Applicability of Public Private Sector Partnership (PPP) in the futuristic Reconstruction in Syria”, The Engineering Sciences Magazine- Faculty of Engineering at Mataria- Helwan University, Vol.148, Issue.1.
Abdel-Alim, A.M. and Said, S.O.M., 2021, “Dynamic Labour Tracking System in Construction Project Using BIM Technology”, International Journal of Civil and Structural Engineering Research ISSN 2348-7607 (Online) Vol. 9, Issue 1, pp.: 10-20.
Abd-Elhamed, A., Amin, H.E. and Abdelalim, A.M.,2020, “Integration of Design Optimality and Design Quality of RC buildings from the perspective of Value Engineering”, International Journal of Civil and Structural Engineering Research ISSN 2348-7607 (Online) Vol. 8, Issue 1, pp.:105-116.
Abdelalim, A.M., El. Samadony, A. and Alaa Al-Harouny, 2016, “Risk Assessment and Mitigation for Construction Projects in Egypt”, the International Conference of Sustainable Construction and Project Management, ICSCPM-16, 29-31March, 2016, Aswan, Egypt.
Abdelalim, A.M. and Said, S.O.M., 2021.” Theoretical Understanding of Indoor/Outdoor Tracking Systems in the Construction Industry”, International Journal of Civil and Structural Engineering Research ISSN 2348-7607 (Online) Vol. 9, Issue 1, pp: (30-36), Month: April 2021.
Abdelalim, A.M. and Said, S.O.M., 2021. “Dynamic labour tracking system in construction project using BIM technology”, International Journal of Civil and Structural Engineering Research ISSN 2348-7607 (Online), Vol. 9, Issue 1, pp: (10-20), Month: April 2021 - September 2021.
Abdelalim, A.M. and Abo. elsaud, Y., 2019. Integrating BIM-based simulation technique for sustainable building design. In Project Management and BIM for Sustainable Modern Cities: Proceedings of the 2nd GeoMEast International Congress and Exhibition on Sustainable Civil Infrastructures, Egypt 2018–The Official International Congress of the Soil-Structure Interaction Group in Egypt (SSIGE) (pp. 209-238). Springer International Publishing.
Abdelalim, A.M., El-Kholy, A., 2016. A comparative study for fuzzy ranking methods in determining economic life of equipment. International Journal of Construction Engineering and Management, 5(2), pp.42-54.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2024 Ahmed Mohammed Abdelalim, Mona Abdelhamid Hassanen, Adel ElSamadony

This work is licensed under a Creative Commons Attribution 4.0 International License.